Page Content
Table of Contents | ||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
|
...
Two dedicated circuits for the monophasic power bars (220Vac 10A), except for OP1400-10 and OP1400-20 which have only one power bar.
One four wire (3 phase + protective earth) cable to connect to the terminal block inside the test bench. This cable must be connected to a 380/400/415 Vac 3 phase circuit.
Refer to 3 Phase AC Mains Supply Line to the PDU (Power Delivery Unit) for the circuit dimensioning requirements.
...
Two dedicated circuits for the monophasic power bars (120Vac 15A), except for OP1400-10 and OP1400-20 which have only one power bar.
One four wire (3 phase + protective earth) cable to connect to the terminal block inside the test bench. This cable must be connected to a 480 Vac 3 phase circuit.
Refer to 3 Phase AC Mains Supply Line to the PDU for the circuit dimensioning requirements.
Please note that it is theoretically possible to have a negative net power flow (energy fed back to the grid) on the 3 phase AC power line. This could be done using, for example, a PV system or a small wind turbine on a DER input of an OP14xx test bench. The user should note that not all electricity distribution companies will allow customers to feed energy to the grid and should contact their local electricity distributor before attempting to do so.
Please also note that OP14x0-10 and OP14x0-20 models will consume steady state unbalanced currents on its 3 phase AC input, which could lead to penalties being imposed to the user by the local electricity distributor.
Contact your local OPAL-RT sales representative for more information if required.
Unpacking
Note |
---|
This equipment has been packaged and shipped in secure conditions. However, when unpacking, check that the equipment has not been damaged during transportation. If there is obvious damage or any signs of knocks which have occurred during transit, please inform OPAL-RT Technologies immediately. |
OP14xx Test Bench Crate
The test bench cabinet and included components will be received in a crate. The following procedure must be executed in order to safely unpack the test bench: Uncrating a Large OPAL-RT Hardware Product.
...
Item | Description | Part Number | Image | Qty |
---|---|---|---|---|
Fiber Optic Transmitters, Receivers SFP | Fiber Optic Transceiver Module 4.25GBd 850nm 3.3V for installation on OPAL-RT simulators to interface through SFP interface | T00-0315 | 1 for each included OP8110 unit | |
Fiber optic cable | Multimode Dplx Fiber Cable 62.5/125 LC-LC 2M to connect OPAL-RT simulators to OP8110 through SFP interface | T00-0797 | 1 for each included OP8110 unit | |
Ethernet cable | CAT6 (500 MHz) UTP Network Cable - Blue 10FT | T00-0817 | 1 for each included OP8110 unit | |
Optical synchronization cable | POF Ind. Plastic Optical Fiber Patch Cords 0.65M | T00-6615 | OP14x0-10: 0 OP14x0-20: 1 OP14x0-30: 1 OP14x0-60: 2 | |
Mini-USB cable | Cable USB A - Mini B Black R/A 3FT | T00-0805 | 1 | |
2m banana cable harness | SLK425-E/N 4 mm safety test lead 200 cm 4 cable harness (Red, Black, Blue and White) | 113-1371 | OP1400-10: 2 OP1400-20: 4 OP1400-30: 6 OP1400-40: 8 OP1400-60: 12 OP1420 models: 4 | |
25 cm white banana cable | SKL425-E/N 4 mm safety test lead 25 cm White | T00-7535 (or T00-8896) | OP14x0-10: 3 OP14x0-20: 6 OP14x0-30: 9 OP1400-60: 18 | |
VFEM cables | Remote Sense cables used for improving the Current Control mode operation. | 113-1427 | 2 sets for each OP8110-6 1 set for each OP8110-3 | |
ITECH Synch cable | On/Off synchronization cable | 113-1588 | These cables are shipped with the ITECH connectors attached. The number of cables change depending on the bench configuration:
| |
Additional components for OP1400-60 with an OP1450 (Applicable for projects delivered after September 1st, 2024) | ||||
VFEM cable | VFEM_sensor_Banana_80inch | 113-1428 | 2 sets | |
VFEM cable | VFEM_sensor_Cosse_120inch | 113-1429 | 2 sets | |
OP1450 power cable | OP1450 power cable set to client system | 113-1383 | 1 set | |
OP1450 jumper cable | OP1450 jumper cable set | 113-1384 | 1 set | |
50 cm banana cable set | SLK425-E/N 4 mm safety test lead 50 cm 4 cable harness (Red, Black, Blue and White) | 113-1377 | 6 sets | |
50 cm single banana cable red | SKL425-E/N 4 mm Safety Test Lead 50 cm Red | T00-7239 | 6 | |
50 cm single banana cable black | SKL425-E/N 4 mm Safety Test Lead 50 cm Black | T00-7240 | 6 | |
ITECH fiber optic cable | ITECH Optical fiber cable for IT6000 and IT8000 | T00-8856 (IT-E168) | 3 | |
External bus bar | Copper bus bar for shorting | 110-3261 | 1 (Installed inside the OP1450 depending on project configuration) | |
Grounding cable | Grounding cable (60inch) to shorting bus bar - 8AWG | T00-6657 | 1 (Installed inside the OP1450 depending on project configuration) |
...
Locate the installation height of the amplifier units using the diagrams below (OP8110-6 amplifiers must be placed on top of OP8110-3 amplifiers if both models are present). The slides are preinstalled on the chassis.
Disassemble the inner portion of the slides by sliding them out and by pushing the lock button, reserve them for step 4.
Detach the mounting screws from the both sides of the amplifier, reserve them for step 4.
Fix the inner rail of the slides onto the amplifiers using the mounting screws.
One amplifier at a time, carefully align the amplifier with the mating slides on the chassis. Once the slides are properly aligned, slide the amplifier into the chassis, pushing on the lock buttons if necessary.
Mount the amplifiers to the chassis side rails using the screws that are already present on the side rails.
...
In the case that an OP8110 unit needs to me removed from the rack either for an RMA or maintenance, ensure to shut down the PDU before opening the cabinet and starting to unscrew the cables. Refer to OP1400 PHIL Test Bench Series Important Safety Information - Accessing the Inside of the Cabinet for detailed procedure.
The OP8110 and DC power supplies will isolate themselves as soon as the PDU is unpowered, eliminating any risk of electric shock.
Note |
---|
Always install the amplifier units one at a time, never having more than one unit hanging on its slides. Failure to do so could cause tilting of the cabinet which could result in serious injury. |
OP1400-10 | OP1400-20 | OP1400-30 | OP1400-40 | OP1400-60 |
---|---|---|---|---|
OP1420-10 | OP1420-20 | OP1420-30 | ||
...
Installation Procedure - Electrical Wiring
Note |
---|
The electrical installation of the OP14xx products must be performed by qualified personnel only. |
The steps for wiring the cabinet are fairly straightforward, the main connections between the test-bench components will be done in the same order as the power flows through the OP1400 test-bench. But before the cabinet is wired the Three-Phase AC Mains to the PDU must be installed. Thus, the steps are as follows:
...
Three-Phase AC Main Supply to the PDU
Note |
---|
The electrical installation of the 3 phase AC mains supply line must be performed by qualified personnel only (Certified Electrician or Lab Technician contracted by the customer) and must be in accordance with local electrical codes which typically include (but is not necessarily limited to) requirements such as:
Failure to do so could result in risks of fire or electric shock. |
Note |
---|
Hazardous voltage levels may be present inside the PDU unit. The supply lines (including monophasic power bars) must be completely disconnected before opening the PDU door. |
After the PDU is connected to the Three-Phase Main, while the PDU is not energized, make sure that the qualified electrician sets the disconnect switches inside the PDU to “ON.” If this step is not done even when energized the PDU will not allow power to flow to the DC power supplies. Refer to the “PDU Connections with the Three-Phase AC Main” section on how the connections need to be made.
...
OP14x0-10/20 models | OP14x0-30/60 models |
---|---|
Warning |
---|
CAUTION: The AC supply lines carry high current, the connections must be properly tightened to avoid resistive connections that could overheat. |
Also, make sure to reinstall the plastic covers on top of the connections to provide protection against electric shock:
...
Use a 5mm Allen key to tighten the DC connections.
Warning |
---|
CAUTION: The DC supply lines carry high current, the connections must be properly tightened to avoid resistive connections that could overheat. |
Also, make sure to reinstall the plastic covers on top of the connections to provide protection against electric shock:
...
OP14x0-30 models | OP14x0-60 models |
---|---|
Warning |
---|
CAUTION: The fiber optic synchronization cablescannot be flexed or folded. Additionally, the OP8110's synchronization cables should neither be connected nor removed during amplifier operation. Doing so mayresult in both damage to the amplifier and voiding of the warranty. |
Info |
---|
OP14x0-10 and OP14x0-20 models don't need synchronization cables since they only have one OP8110 unit. |
Cable Routing
The customer power cable must be routed through the rear door of the OP14xx chassis.
...
Expand | ||
---|---|---|
| ||
The OP1400-40 models require the Medium Power PDU version. This setup provides over current protection fuses for the Itech cables. For these models, the 3 lines plus the ground wires must be connected to the bottom of the customer power terminals.
The AC Input cable and the Itech Power Supplies cables pass via cable clamps located at the bottom of the box. |
...
Expand | ||
---|---|---|
| ||
The OP1400-60 models require the High Power PDU version. This setup provides over current protection fuses for the Itech cables. For these models, the 3 lines plus the ground wires must be connected to the bottom of the customer power terminals.
The AC Input cable and the Itech Power Supplies cables pass via cable clamps located at the bottom of the box. |
...