HIL2GO-410 - System Power On and Power Off Sequences

Page Content

TARGET COMPUTER RE-BOOT WARNING: Follow the Power On/Off sequence as indicated below. Failure to do so may require rebooting of the Target.

image-20240729-160137.png
Power on and power off sequences

Power on Sequence

  1. Power on the OP4810-IO

  2. Power on the OP5025XG

If the OP525XG (which is running HYPERSIM on the target) is powered on before the OP4810-IO, HYPERSIM won't be able to detect the present of OP4810-IO FPGA Processor and I/O Expansion Units.

Power off Sequence

  1. Power off the OP5025XG

  2. Power off the OP4810-IO

Disconnecting or powering off the OP4810-IO during operation will require a power off sequence followed by a power on sequence in order to resume reliable operation.