OP1200 Installation

Connecting Cables

The MMC Test Bench is shipped with units already mounted in the rack and cable assemblies completed. However, there are certain cables that must be connected:

  • Connect the auxiliary power bar
  • The auxiliary power bar is affixed to the bottom of the rack and all units are connected.
  • You need only plug the power bar into an approved power outlet as shown in Figure 4.



Make sure that the rack is configured for the appropriate local voltage (120V or 240V).



Connecting the Auxiliary Power Bar


  • Connect the Ethernet cable from the OP4510 to the nearest network jack, as shown.



  • Connect grounding wire for the entire rack (optional: if high voltage cables are not already grounded).
  • Connect high voltage cables to the protection box (refer to the diagram shown in Figure 14).

You are now ready to power up your MMC Test Bench.


Connecting the Optional, Independent Ground Wire to the Rack


Because it is connected to hazardous voltages, the OP1200 MMC Test Bench must be properly grounded at all times.